Projects Gallery

The following is illustrative view of some major facilities developed under PMC between the years 2013 -2017. It is noted that some are on the final phase and shall be handover soon the client once complete test are conducted.

WATER TREATMENT PLANT & FACILITIES AT MELUT&PALOCH OBC

  • Contract NO: DPOC/23/12-1280
  • Design Capacity: 4800 m3/Day
  • Vendor (s) involved: N/A
  • Project contract value: $ 21.9M
  • Commissioning Period: January – February 2016
  • Commissioning status: Successfully commissioned

FIELD REJUVENATION WORK

  • Contract NO: DPOC/23/14-1886A
  • Design Capacity: 500 m3/Day
  • Vendor involved during commissioning: Mena Water
  • Project contract value: N/A
  • Commissioning Duration: February-March, 2016
  • Commissioning status: Successfully commissioned
  • Handed over to DPOC date: March 2016

DEBOTTLENECKING PROJECT (SEDIMENTATION PROCESS CASE I)

  • Contract NO: DPOC/23/13-1193
  • Design Capacity: 818600 BFPD (200,000 BOPD, 10 WC%V, 584100 BFPD Normal case (143100 BOPD, WC%V)
  • Project contract value: $ 102.6 M
  • Commissioning status: Complete
  • Handover to DPOC date: TBD